The concrete bridge was constructed to substitute old Shamozai bridge over River Swat which had swept away during the 2010 flash-floods. UAE Government financed the reconstruction of bridge.
Fact Check:
- Commenced : 2011
- Completed : 2013
- Length : 0.48 km